VVC’s PHC Drills the First Two New Wells in its Syracuse Project - Contracts Given for the Syracuse Project Gas Gathering System
Sep 28, 2021

VVC Exploration Corporation ("VVC" or the "Company") (TSX-V:VVC) is pleased to announce that its wholly owned subsidiary Plateau Helium Corporation (PHC) has drilled two new gas wells on the Syracuse Project, each of which showed two zones of helium gas. PHC has contracted with TMI Solutions, LLC for engineering and with Eatherly Constructors, Inc to build an internal gas gathering system for the Syracuse Project. PHC continues to acquire additional helium lease acreage as it expands its footprint in the helium business and commences commercial helium and natural gas production at the Syracuse Project.


Incredible Progress by PHC


VVC President Jim Culver took the opportunity to praise the PHC team for the incredible business progress since VVC took over PHC. "These two wells mark the beginning of commercial helium and natural gas production in our Syracuse Project. Eight (8) more wells are permitted and being prepped for drilling. In addition to the four (4) helium projects that PHC now has, it continues to look for opportunities in the helium sector. I want to thank the Team for their hard work and VVC’s investors and shareholders for supporting this transformative effort."


He also noted that VVC recently acquired an investment position in a promising startup resource company, Plateau Carbon LLC (PCL). PCL has since acquired a large industrial gas lease holding that includes carbon dioxide ("CO2"), nitrogen and helium. Plateau Carbon's primary purpose is the geologic sequestration of CO2 in an effort to aid in the reduction of US carbon emissions. The secondary focus is the production and sale of helium.


Commencement of Commercial Production on Syracuse Project


The Durler 2-21 is the first new well drilled on the Syracuse Project and two gas zones were encountered. One zone was perforated and flowed gas while and the second zone indicates gas but has not yet been tested. The well will be completed and connected to the pipeline as soon as the internal gas gathering system connection is available, sometime in Q4, 2021.


PHC’s second Syracuse well is the Levens #2. The same two gas zones were encountered in Levens #2 as in the Durler 2-21. This well was perforated in the same zone as the Durler 2-21 and also flowed gas. And like the Durler 2-21, an additional zone indicative of gas production was encountered which has not yet been perforated. Levens #2 is located very near the Tumbleweed pipeline and is scheduled to be completed, tested and connected to the Tumbleweed pipeline by mid-October.


Site preparation has begun on 8 additional newly permitted Syracuse well locations with drilling to commence in Mid-October 2021 and be completed in December 2021. PHC expects to have a total of ten (10) new wells completed and producing in the Syracuse Project by the end of December of 2021.


The Company also plans to drill twenty (20) additional new wells in Syracuse in the first half of 2022.


Syracuse Internal Gathering System and Tumbleweed Pipeline Connection


PHC has contracted with TMI Solutions, LLC for engineering and Eatherly Constructors for construction of an internal gas gathering system in the Syracuse project. The core of this gathering system will start at the Levens #2 well and connect the Durler 2-21 and the eight (8) other wells to be drilled before the end 2021, in an approximately 15-mile system. This Syracuse Gathering System will provide convenient connector points for balance of the 160 potential well sites in the Syracuse Project.


Continued Acreage Acquisition and Expansion of Syracuse Extension


PHC’s Syracuse Extension has been divided into two separate projects. The first, includes leases in two (2) counties in Western Kansas, now referred to by the Company as Syracuse Extension Kansas; the second includes leases in four (4) counties in Eastern Colorado now referred to by the Company as Syracuse Extension Colorado. Historically, the leases in these two projects was evaluated by proximity to historical wells that tested helium rich natural gas. Because of low natural gas prices at the time of drilling, and lack of access to helium processing these wells were not completed, nor put into production, and were subsequently plugged.


PHC's Helium Projects


PHC now has four (4) helium projects, presently covering an aggregate of approximately forty thousand (40,000) acres: the original Syracuse Project, Monarch Project, Syracuse Extension Kansas, and Syracuse Extension Colorado. Upon completion of the core leasing, the total leases in these four (4) projects is expected to be over seventy-five thousand (75,000) acres with over six hundred (600) potential well locations. In addition to the core acreage in each of these projects, the Company will continue to add properties to each project on an "as available" basis.


  • The Syracuse Project initially consisted of 13,440 acres of gas leases located in Hamilton County, Kansas. PHC continues to add to the leased acreage on an opportunistic basis with the present total standing at over 16,000 acres. This project is the focus of PHC’s initial new well drilling and production campaign. Two (2) new wells have been drilled, and are awaiting testing, completion and pipeline connection. Eight (8) more well sites have been permitted and site work has begun. Drilling is scheduled to begin in mid-October with completion, including pipeline connection, before year end. The first new well is expected to be connected to the pipeline in October.


  • The Monarch Project consists of 1,600 acres of gas leases located in Greeley County, Kansas with six existing wells that are in the late stages of their productive life. At this time, five (5) of these previously producing wells have been re-connected to the pipeline and are producing helium rich gas. The focus in this Project is the 14 additional potential well locations which are conveniently located for connection to the Tumbleweed pipeline.


  • Syracuse Extension Kansas’s initial targeted acreage was 8,540 acres of which 3,320 acres have completed leases and still 5,220 acres are in process. The targeted acreage has twenty-four (24) wells on acreage already leased and 17 on acreage, in process, that were previously drilled and tested helium rich natural gas but were plugged for lack of a viable market. Other acreage will be added to this Project as it is available. The project with its present leased acreage has 138 potential well locations. Initial new well drilling is scheduled to commence in Syracuse Extension Kansas in Q4 of 2021. Six wells are currently in the process of being permitted.


  • Syracuse Extension Colorado has now leased 17,747 acres of its targeted core of 20,187. In addition, PHC is completing a development contract with a major mineral owner for an additional 28,160 acres. There are a total of 28, tested but not producing wells in the project. The Company expects to complete this leasing and contracting by the end of October. PHC has begun the permitting process for the first Syracuse Extension Colorado wells and expects to drill the first well in Q1 2022.


Helium Value

Helium prices and demand have continued to increase as the US Strategic Helium Reserve has been depleted. In addition to the more traditional uses in welding and industrial processing, helium is a key item in high tech manufacturing, medical devices and space programs.


Global Investment Daily described the ' Helium Boom that is about to take off in 2021 ' (https://globalinvestmentdaily.com/the-helium-boom-is-about-to-take-off-in-2021) and price wise it certainly has. Long term contract prices for helium (five-year and ten-year contracts) have increased by as much as 25% during 2021, and spot prices in some cases appear to have doubled, making helium one of the most profitable commodity products in the last five years. Even at the low end of the range for the projected five-year average price for helium, PHC could have a significant profit margin on its helium business based on the costs to date for drilling and servicing wells and the existing contract price for helium.


A few companies are now pursuing helium production, but the areas where commercial helium wells have been found are limited. PHC has been aggressively acquiring lease acreage in areas where there has been past production of helium, to allow the Company to grow its helium business rapidly.



PHC’s helium business has the potential to become highly profitable if it can ramp up commercial production over the next 24 months and continues to acquire leases that have a high likelihood of profitable helium production.

09 May, 2024
If you take helium gas and you cool it at atmospheric pressure to 4.2 K in becomes a liquid. Keep cooling to 2.2 K and the helium enters its superfluid phase, called helium II. Superfluid helium has several very useful properties and is used in science and technology in multi-tonne quantities today. In particular, helium II is an exceptionally good conductor of heat and this combined with its low temperature means that the superfluid is ideal for cooling components made from superconducting materials.
07 May, 2024
The production of lithium (Li) and nickel (Ni), two key raw materials for batteries, can produce vastly different emissions profiles. This graphic from Wood Mackenzie shows how nickel and lithium mining can significantly impact the environment, depending on the processes used for extraction.
Show More >
Share by: